Tikhaya Digital Substation: Automated Process Control System Manages Power Supply to Ingushetia’s Agricultural Complex
The 330/10 kV Tikhaya substation will supply electricity to Sunzha, the largest agricultural complex in the Republic of Ingushetia. The newly commissioned facility uses state-of-the-art automated process control systems (APCS) integrated into the power system’s operational dispatch control framework.

The Tikhaya substation is designed to ensure a reliable power supply to an agricultural complex that grows vegetables year-round and produces more than 15,000 metric tons annually. Sunzha uses advanced lighting, pollination and climate-control systems across a total area of 22 hectares. Reliable electricity supply is therefore particularly important to its operations.
The substation is equipped with two 330/10 kV transformers, each rated at 63 MVA. Either transformer can independently supply the required peak load of 42 MW. This means the agricultural complex can continue operating without interruption if one transformer fails or is taken out of service for scheduled maintenance.
The substation features a digital automated process control system (APCS) that not only monitors all equipment operating parameters but also enables remote operation of Tikhaya from the dispatch center of the North Caucasus Regional Dispatch Office (North Caucasus RDO). This significantly improves response times and operational safety when switching operations are carried out across the regional power system. The APCS also collects telemetry and transmits equipment status data to dispatchers.
Several branches of System Operator of the Unified Power System JSC (SO UPS) took part in the project, including the Southern Unified Dispatch Office (Southern UDO) and the North Caucasus RDO. The substation uses Russian-made transformers and an APCS running on a domestic software platform.

From Remote Switching to Intelligent Monitoring
The commissioning of Tikhaya reflects a broader trend that has gathered pace in recent years: digital systems and remote control of power facilities are becoming standard industry priorities. Modern APCS deployments also make it possible to collect large volumes of operational data from equipment. Over time, this information could be processed using neural network algorithms. Predictive analytics would help identify early signs of equipment wear and schedule maintenance before failures occur. At the level of larger sections of the power grid, data from digital substations could also support more effective operating-mode management, faster switching operations and better forecasts of increases or decreases in electricity demand.
Growing demand for digital control systems is also creating opportunities for Russia’s IT sector. Equipment manufacturers are continually improving their hardware components, while software developers are refining control algorithms. Many Russian products are already comparable in quality to foreign alternatives, potentially making them competitive in the markets of countries friendly to Russia.

Remote Control: From Lebedi to Narva
Tikhaya is not a first-of-its-kind project but builds on an established approach. In 2021, remote equipment control was introduced at the 330 kV Lebedi substation in Belgorod Region. The same approach was deployed in 2022 at the 220 kV Teya substation in Khakassia and in 2023 at the 330 kV Murmanskaya substation.
In 2024, the existing practice was given a legislative framework. Amendments to the Federal Law on the Electric Power Industry made remote monitoring systems mandatory at all electric grid facilities operating at voltages above 220 kV. The legislation also formally introduced the term “digital information model of an electric power facility.” More broadly, the industry has been moving deliberately away from managing individual facilities toward coordinated management of entire sections of the electricity grid.
For Ingushetia, the commissioning of Tikhaya means more than the addition of another modern substation to the regional power system. It is expected to improve the controllability and reliability of the republic’s entire energy infrastructure while supplying electricity to Sunzha, one of its largest agricultural complexes in Ingushetia. The facility makes a significant contribution to the country’s food security and creates new jobs in the region.