TsNIITMASH Deploys Digital Solutions to Speed Up Equipment Installation at Nuclear Plants

This has reduced the production time for a number of critical components.

Photo: atommedia.online

The Central Research Institute for Machine-Building Technology research and production association has deployed a whole set of production and digital solutions to improve the efficiency of large infrastructure projects. Specialists were able to significantly optimize the production time for embedded parts that serve as the foundation for installing key nuclear plant equipment.

Embedded structures are installed into the building elements of nuclear power units before the main process equipment is mounted. They ensure reliable fastening of all large components. The work was carried out under an industry project aimed at introducing lean manufacturing principles and improving resource efficiency.

"Within the project, bottlenecks were analyzed, equipment loading was redistributed, the sequence of operations was optimized, and the work of divisions was synchronized. As a result, the production time for certain items and assemblies was cut by a factor of 1.5 to 2. Digitalization of production management became an important part of the project. At TsNIITMASH, end-to-end network schedules for contract execution have been automated, making it possible to promptly redistribute resources to complete work stages," said Ilya Litvinov, Director of Pilot Production at the TsNIITMASH research and production association.

like
heart
fun
wow
sad
angry
Latest news
Important
Recommended
previous
next